F Wing - Presbyterian Hospital


"We were well ahead of our schedule. The system went together even faster than expected!" - Drew Robinson

Description 100,000 sf, 4 story, vertical addition, 75 beds, - topped out in 16 weeks, saved $1M in operational and construction costs

Solution
Kore-Flex Columns, VERSA:T: Beams, Steel Bracing, and Deep-Dek Composite floor system

Overview
Building across 2 different structural systems, tieing back to adjacent buildings, not wanting to disrupt hospital operations, and all the while confined by floor to floor heights - that was the situation for Novant and ultimately why DIVERSAKORE & CSi were the right solution.
  Developer Novant
Architect McCullough & England
Structural Engineer DIVERSAKORE/Browder Leguizamon
General Contractor Rodgers Builders

Fabricator Macuch Steel Products
Steel Deck Supplier CSi Metal Dek Group
Cast In Place Contractor Precision Concrete
Erector Shumake